Investment Proposal
          "Сonstruction and Maintanance of Cultural and Sport Complex-"Surozh"
          
         1. Mission 
          of the Investment Proposal
1. Mission 
          of the Investment Proposal
          To construct and reconstruct the existing buildings in ordrer to create 
          a cultural and sport complex with covered grand stands for 5000 places 
          and a hotel for 100 customers to conduct football matches and other 
          sport competitions, concerts and cultural activities. 
          Nowadays there is no a cultural and sport complex similar to the proposed 
          in the project in Sudak and Crimea. The proposed for the construction 
          is unique with its comprising components.
          The Complex could be exploited all year round. The given Complex could 
          be used as a training base for United Ukrainian Army Football Team and 
          other football teams. 
        Picture 1. Location of the existing stadium
        The planned complex is unique on structure of included components.
        For the Project realization a joint venture could be created under 
          the condition: 
          - "Surozh" Sudak Football Club on agreement with municipal 
          executive body gives a land lot with the square of 2 hectars renting 
          it without charge;
          - an investor pays expenses for constructing the Complex and equipping 
          the Center and territory improvement;
        
        Preliminary costs are calculated according to the standards taking 
          into account every necessary expenditures, new technologies, technological 
          solution complexity and construction conditions are included.
        Preliminary Complex costs are 5 724 000 USD. Duration of the Complex 
          construction is 2.2 years.
        The Project realization allows provide sport competition and cultural 
          activities (football matches, sport competitions, concerts and festivals) 
          for the city population and its guests, hotel services, feeding sportsmen 
          and actors, for people having their rest in Sudak, giving other additional 
          services.
          One of the attractive features of the Project proposed is children ground 
          where children could spend their time while parents are watching concerts, 
          competitions, etc.
        
        Existent situation
          Today the existing stadium is not used for its main purpose. The existing 
          stadium construction and the land lot with the area of 2 hectares where 
          they are situated are the base of "Surozh" Sudak Football 
          Club but is not used on the direct destination. The land lot and stadium 
          constructions are in the long-term leasing of the "Surozh" 
          Sudak Football Club (50 years) since 1998. "Surozh" Sudak 
          Football Club is the non-government sports - health organization and 
          operates under the state privileges.
        The stadium is located in the center of the city, in a park zone, The 
          Black Sea is 100 meters from it.
        
         
 
        Picture 2. View at existing stadium in Sudak
        Coefficients of economic efficiency for 9 years of the project 
        - Net profit with the saved up result - 4,2 million USD;
          - Internal rate of return (IRR) - 18 % (15 лет проекта);
          - Cost benefit ratio (CBR) - 0,86 (at the rate of discounting of 12 
          % annual);
          - Payback period (PP), discounted - 11,4 years (at the rate of discounting 
          of 12 % annual);
          - Payback period (PP), not discounted- 7,4 years;
          - Profitableness index (Pi) -1,63 .
          - Depreciated cost of fixed capitals excluding ground and business cost 
          - 2,9 million of USA dollars.
        Above-listed factors are counted by a common method with discounting 
          method application without depreciated cost (liquidation value) of the 
          project.
        
        Экономическое влияние проекта и его социальная значимость
        
         As a result 
          of the project 80 workplaces will be embed at the third year of the 
          project. The object of sports and amusements will be constructed and 
          it should to exert essential influences on Sudak as the favorable sports 
          and cultural place that provide an additional vacationers and sportsmen 
          at off-season. At the state budget should be attracted additional taxes 
          in 2,3 million USD for 9 years of the project.
As a result 
          of the project 80 workplaces will be embed at the third year of the 
          project. The object of sports and amusements will be constructed and 
          it should to exert essential influences on Sudak as the favorable sports 
          and cultural place that provide an additional vacationers and sportsmen 
          at off-season. At the state budget should be attracted additional taxes 
          in 2,3 million USD for 9 years of the project.
        As the basic results of the project: 
          " Construction of the modern cultural - sports Complex;
          " Attraction of the football and other teams for competitions and 
          trainings, attraction of the artists and singers groups for cultural 
          acting;
          " Maintenance of steady development of the enterprise due to strategy 
          of the advanced complex of sporst -cultural complex granting sports, 
          amusement, cultural and other services;
          " Maintenance of gross revenues of the enterprise in the sum of 
          2,1 million USD (since 9-th year of the project), and net profit more 
          than 0,7 million USD at the same period.
        
         To get additional information on the Project please address Economics 
          Department Executive Committee of Sudak Municipal Bodies: Crimean Autonomous 
          Republic, tel.(06566)22096, fax 22492
        Contact person: Vladimir Arkadievich Novikov, Deputy major, tel. (06566) 
          22391. 